Mpakeni Dam construction hits 31 per cent

Share
The second milestone of the project is the diversion channel which was operationalised to give way for the construction of the Diaphram Wall. (Courtesy pic)
Share

MBABANE – Construction of the game-changing Mpakeni Dam under the MNWAP has officially passed the 31 per cent completion mark, signalling significant progress in one of Eswatini’s most ambitious water infrastructure projects.

Driven by the Eswatini Water and Agricultural Development Enterprise (EWADE), the project is not only transforming the landscape of Shiselweni, but also setting new standards in infrastructure delivery and national empowerment.

According to Project Resident Engineer Valey Vilane, these landmarks have been achieved despite early setbacks ranging from abnormal rainfall, material shortages and protracted labour disputes, construction contractor Sakhalive Joint Venture, a consortium between Chinese engineering giants Sinohydro and Yellow River, has delivered critical milestones ahead of schedule and within budget.

Their performance is part of a broader Mkhondvo – Ngwavuma Water Augmentation Programme (MNWAP) vision spearheaded by EWADE to ensure water security, agricultural transformation and socio-economic upliftment.

Among the most notable milestones is the successful completion of the permanent camp, comprising employer and engineer offices, which was delivered within a scheduled 124-day window, From February 1 – September 12, 2024, without cost overruns, Vilane told the Times Business Desk.

Vilane went on to disclose that another landmark achievement was the early completion and commissioning of the diversion channel, using over 40 000 cubic metres of concrete.

Originally due by June 30, water was successfully diverted through the channel on June 26, 2025, four days ahead of schedule.

“These milestones are enabling seamless work on core dam structures. Currently, spillway excavation is over 50 per cent complete, the diaphragm wall, a critical seepage control feature is at 36 per cent completion and it is being installed under technically challenging geological conditions,” Vilane said.

Meanwhile, EWADE’s technical leadership has ensured the integrity of timelines and quality control, with its engineers providing continuous supervision and mentoring.

Full article available in our paper.

Share
Written by
Nhlanganiso Mkhonta

Nhlanganiso Mkhonta serves as Business Editor at the Times of Eswatini. He reports on business, economics, finance, investment, entrepreneurship and public policy, producing insightful coverage and analysis of the issues driving Eswatini’s economy and the wider African business environment.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

Bugwadla, infidelity won’t get you to hell – pastor

LOBAMBA – For many preachers, there is only one place for people who engage in bugwadla (habitual sexual misconduct) and kuphinga – hell....

Cop launch investigation after ‘priest’ tied up, robbed

HLUThI - Police have launched an investigation following an armed robbery at Our Lady of Sorrows Mission, where a 50-year-old priest was bound...

E2bn Chinese fraud suspect fears death penalty

MBABANE – The Chinese national, Jin Houyun, who is suspected of involvement in pooling over E2 billion from thousands of investors in China...

Board orders Mfabantfu church reopening

MANZINI – The Apostolic Faith Church International Board has resolved that the Mfabantfu branch will resume church services in a month’s time. This...

ICC projected to generate E50 million annually

MBABANE – Barely three months after it was commissioned by His Majesty King Mswati III, the Ezulwini Palazzo International Convention Centre (ICC) is...

Related Articles

Beef production generates E140.4m in Q1

MBABANE – Eswatini’s agricultural sector delivered a resilient performance during the first...

Eswatini accelerates trade reforms

MBABANE - Eswatini has taken significant step towards strengthening its position as...

PSPF investment income surges to E3.4bn

MBABANE – The investment arm of the Public Service Pensions Fund (PSPF)...

ESE tops E7bn despite trading slowdown

MBABANE – Eswatini’s stock market demonstrated remarkable resilience during the second quarter...